Paid Deposit to MJH/ Signed Prelim Agreement 02/8/2014
Land Settlement 05/8/2014
Acceptance of Final Consolidated Tender 15/8/2014
Colour Walkthrough 18/8/2014
Colour Selection Day 25/9/2014
Signed off on Preliminary Plans 25/9/2014
Building Agreement Signed 09/10/2014
Building Approvals / DA to Council 10/10/2014
Electrical Appointment 06/11/2014
DA Approval 13/11/2014
Authority to Commence Construction 13/11/2014
Construction List 13/11/2014
Site Start (cut) 27/11/2014
Slab 08/12/2014
Frame 12/12/2014 - 20/12/2014
Bricks 23/12/2014- 12/01/2015
Roof 21/01/2015- 22/01/2015
Electrical and Plumbing rough in (inspection) 06/02/15
Indoors (linings, kitchen, tiling)
- Gyprock/ Plaster 09/02/15- 28/02/15
- Bathrooms (tiling) 21/03/15
-Painting finished 31/03/15
- Plumbing complete 31/03/15
- Electrical complete 02/04/15
-Flooring complete 13/04/15
Practical Completion
Handover