Timeline

Paid Deposit to MJH/ Signed Prelim Agreement                       02/8/2014
Land Settlement                                                                          05/8/2014
Acceptance of Final Consolidated Tender                                 15/8/2014
Colour Walkthrough                                                                  18/8/2014
Colour Selection Day                                                                  25/9/2014
Signed off on Preliminary Plans                                                 25/9/2014
Building Agreement Signed                                                       09/10/2014
Building Approvals / DA to Council                                          10/10/2014
Electrical Appointment                                                               06/11/2014
DA Approval                                                                              13/11/2014
Authority to Commence Construction                                      13/11/2014
Construction List                                                                       13/11/2014
Site Start   (cut)                                                                           27/11/2014
Slab                                                                                             08/12/2014
Frame                                                           12/12/2014 - 20/12/2014
Bricks                                                            23/12/2014- 12/01/2015
Roof                                                               21/01/2015- 22/01/2015
Electrical and Plumbing rough in (inspection)                       06/02/15                         
Indoors (linings, kitchen, tiling) 
- Gyprock/ Plaster                                                  09/02/15- 28/02/15
- Bathrooms (tiling)                                                21/03/15
-Painting finished                                                    31/03/15
- Plumbing complete                                               31/03/15
- Electrical complete                                                02/04/15
-Flooring complete                                                   13/04/15            
Practical Completion
Handover